Sunday, July 14, 2019

Financial Report - July 11, 2019

This is latest update
 
 
1. Ceilings - 15000 PLN
2. Floor Tiles hall stairs,  only work  - 5300
3. Bathrooms sinks. pisuars.  WC - 4200
4. VINYL PANEL FLOOR- 16000
5. Doors inside- PORTA- 15pcs - 14000PLN
6. Central Ventilation - 12500 PLN
7. Painting - 3400 PLN
8. Kitchen Tiles and work  -3000
9. Electrical equipment + lamps - 4500
10. WALLS plaster  - 18000
11. Bathroom wall  dividers - 4400
 
sum:  100.300 PLN
 
 
OUTSIDE
1. Doors (2pcs ) - 8300 PLN
2. Heating Pump - 45000 PLN
3. Providing Water (100m) - 11000
4. Draining System - 8000PLN
5. WATER Harvesting system, Rain water system  - 12000PLN
 
 
SUM: 43800 PLN
 
OUTSIDE INSIDE SUM : 144.100PLN
 
At this moment we have ca 80.000 PLN
 
Greetings
 
Zbyszek Hanaczewski
 

** Note: The difference of 64,000 PLN is roughly $17,000.